Dredging is currently occurring in:

The Entrance of Port Phillip Bay (Project Area 4)

Yarra River (Project Area 1)

Port Melbourne Channel (Project Area 2)

Vessel undertaking works: 

Trailer Suction Hopper Dredge,Queen of the Netherlands  (Entrance)

Grab Dredge, Goomai (Yarra River)

Trailing Suction Hopper Dredge, Cornelis Zanen (CoZa)

Dredge material placed in:

South East Dredge Material Ground (Material from Entrance) 

Port of Melbourne Dredge Material Ground, Confined Aquatic Disposal Facility (Material from Yarra River and Port Melbourne Channel)

Visible outcomes of works: Turbid plumes can be expected in the vicinity of dredging works.

Please maintain a safe distance from dredging equipment at all times. For information on restricted access areas around vessels please follow this link.

 

Further information on daily activities in each project area are available in the tables below (n/a = no activities):

Project Area 1: Yarra River & Hobsons Bay 

Dredging works:   The grab dredge, Goomai,   is scheduled to continue dredging in the Yarra River today

 

 

Project Area 2: North of Bay

Dredging works: The CoZa is scheduled to continue clay dredging and bund construction in the Port Mebourne Channel.

 

 

Project Area 3: South of Bay

Dredging works: n/a

Project Area 4: The Entrance

Dredging works:  Queen of the Netherlands is scheduled to dredge on the Rip bank at the Entrance of the bay.

 

 

PLEASE NOTE: The information on this page is subject to change. For further information on the location of dredging activities please call toll free 1800 731 022.

Daily activity updates will be provided on weekdays outlining the planned works for the next 24 hours (am to am). The Friday daily activity update will outline the planned works for that day and the weekend to follow (Friday am to Monday am).

 

Project Areas and Dredging Locations

Page last updated:       24 June 2008