Dredging is currently occurring in:
The Entrance of Port Phillip Bay (Project Area 4)
Yarra River (Project Area 1)
Port Melbourne Channel (Project Area 2)
Vessel undertaking works:
Trailer Suction Hopper Dredge,Queen of the
Netherlands (Entrance)
Grab Dredge, Goomai (Yarra River)
Trailing Suction Hopper Dredge, Cornelis Zanen
(CoZa)
Dredge material placed in:
South East Dredge Material Ground (Material from
Entrance)
Port of Melbourne Dredge Material Ground, Confined Aquatic
Disposal Facility (Material from Yarra River and Port Melbourne
Channel)
Visible outcomes of works: Turbid plumes can be
expected in the vicinity of dredging works.
Please maintain a safe distance from dredging equipment at all
times. For information on restricted access areas around vessels
please follow this link.
Further information on daily activities in each project area are
available in the tables below (n/a = no activities):
|
Dredging works: The grab
dredge, Goomai,
is scheduled to continue dredging
in the Yarra River today
|
|
Dredging works: The CoZa
is scheduled
to continue clay
dredging and bund construction in the
Port Mebourne Channel.
|
|
Dredging works: Queen of
the Netherlands
is
scheduled to dredge on the Rip bank at the Entrance of the bay.
|
|
PLEASE NOTE: The information on this page is subject to change.
For further information on the location of dredging activities
please call toll free 1800 731 022.
Daily activity updates will be provided on weekdays outlining the
planned works for the next 24 hours (am to
am). The Friday daily activity update will outline
the planned works for that day and the weekend to
follow (Friday am to Monday am).