Dredging is currently occurring in:

Yarra River (Project Area 1)

Port Melbourne Channel (Project Area 2)

South of Bay (Project Area 3)

Vessels undertaking works: 

Trailer Suction Hopper Dredge,Queen of the Netherlands

Grab Dredge, Goomai  (Yarra River, Williamstown Channel)

Trailing Suction Hopper Dredge, Cornelis Zanen (CoZa)

Backhoe Dredge, Storken (Yarra River, services protection)

Backhoe Dredge, Ain D'Schalut  (Yarra River)

Dredge material placed in:

South East Dredge Material Ground (Material from Entrance) 

Port of Melbourne Dredge Material Ground, Confined Aquatic Disposal Facility (Material from Yarra River and Port Melbourne Channel)

Visible outcomes of works: Turbid plumes can be expected in the vicinity of dredging works.

Please maintain a safe distance from dredging equipment at all times. For information on restricted access areas around vessels please follow this link.

Further information on daily activities in each project area are available in the tables below (n/a = no activities):

Project Area 1: Yarra River & Hobsons Bay 

Dredging works:   

The grab dredge Goomai is scheduled to dredge in Swanson Dock today and over the weekend.

The Storken is scheduled to dredge in Gellibrand Swing Basin and undergo maintenance.

The Ain D'Schalut  is scheduled for maintenance.

Please note changed traffic conditions now apply in the Yarra River. For more information click here>>

Project Area 2: North of Bay

Dredging works:

Project Area 3: South of Bay

Dredging works:  TheQueen of the Netherlands and the CoZa are both dredging in South Channel.

Project Area 4: The Entrance

Dredging works: n/a

PLEASE NOTE: The information on this page is subject to change. For further information on the location of dredging activities please call toll free 1800 731 022.

Daily activity updates will be provided on weekdays outlining the planned works for the next 24 hours (am to am). The Friday daily activity update will outline the planned works for that day and the weekend to follow (Friday am to Monday am).

Project Areas and Dredging Locations

Page last updated:                          3 July 2009

To access archived daily updates follow this link.